this post was submitted on 23 Dec 2024
723 points (99.1% liked)

World News

39385 readers
2312 users here now

A community for discussing events around the World

Rules:

Similarly, if you see posts along these lines, do not engage. Report them, block them, and live a happier life than they do. We see too many slapfights that boil down to "Mom! He's bugging me!" and "I'm not touching you!" Going forward, slapfights will result in removed comments and temp bans to cool off.

We ask that the users report any comment or post that violate the rules, to use critical thinking when reading, posting or commenting. Users that post off-topic spam, advocate violence, have multiple comments or posts removed, weaponize reports or violate the code of conduct will be banned.

All posts and comments will be reviewed on a case-by-case basis. This means that some content that violates the rules may be allowed, while other content that does not violate the rules may be removed. The moderators retain the right to remove any content and ban users.


Lemmy World Partners

News !news@lemmy.world

Politics !politics@lemmy.world

World Politics !globalpolitics@lemmy.world


Recommendations

For Firefox users, there is media bias / propaganda / fact check plugin.

https://addons.mozilla.org/en-US/firefox/addon/media-bias-fact-check/

founded 2 years ago
MODERATORS
 

Summary

France’s Flamanville 3 nuclear reactor, its most powerful at 1,600 MW, was connected to the grid on December 21 after 17 years of construction plagued by delays and budget overruns.

The European Pressurized Reactor (EPR), designed to boost nuclear energy post-Chernobyl, is 12 years behind schedule and cost €13.2 billion, quadruple initial estimates.

President Macron hailed the launch as a key step for low-carbon energy and energy security.

Nuclear power, which supplies 60% of France’s electricity, is central to Macron’s plan for a “nuclear renaissance.”

you are viewing a single comment's thread
view the rest of the comments
[–] Resonosity@lemmy.dbzer0.com 3 points 2 days ago (1 children)

Bro, THE FUCKING BACKUP DIESEL GENERATORS FOR THE PLANT WERE BELOW SEA LEVEL.

Make it make sense. If those generators had been above sea level, well probably above 100-year tsunami levels, we likely would not have seen the plant catastrophically fail.

[–] Rhaedas@fedia.io 3 points 2 days ago (1 children)

That was part of the problem. Built where it was cheaper, ignoring literal ancient markers saying not to live there because of the past. But they would have still not failed, had they been designed for the potential of being submerged. Again, they were not because that would cost more for a long range risk. It all falls into bad planning and profit, not in any way because it was a nuclear plant.

[–] zqps@sh.itjust.works 1 points 2 days ago

bad planning and profit are of course words never uttered in connection with German infrastructure projects.